1 – First meeting and review of the project based on architects drawings for a first estimation and timing of your project.
2 – Architectural drawings (1 – 6 months). Please look at partners to meet with the architect the most adapted to your project.
3 – Structural studies and small scale models in order to ensure stiffness, durability and define together the best options for your project. (2 weeks – 4 months) A related quotation as well as estimated planning of construction for the bamboo building will be proposed at this stage.
4 – Once contracts are signed and deposit done, we will prepare the bamboo material and teams, transport of material (1 – 2 months)
5 – Bamboo construction (1 – 6 months). The foundations should be built with a local contractor or partners before installing the bamboo structure. Electricity and plumbing can be prepared as well. (1 – 4 months)
- Bamboo columns
- Roof bamboo structure
- Roofing
- Finishing on bamboo structure
6 – Delivery of the bamboo structure, interiors and landscaping
7 – Grand Opening!